A stunning drone shot captured by a CME team member showcases the ongoing progress on the Sparks Boulevard Project, just south of the Baring Blvd. intersection.
In the foreground, crews are backfilling over the 337-foot RCB extension, which connects to two new retaining walls forming on each side of the channel. Further down, you can see active wetland mitigation work and slope grading that will support the upcoming roadway expansion, and on the left side of the image, drilling is underway for the new soundwall foundations.
Progress from every angle and more to come!